Time fence means

  • 1. The shortest lead-time from raw material to finished production of an item
  • 2. Ensuring accuracy of inventory records
  • 3. Method used to update MRP at regular intervals
  • 4. Calculating net requirements of components

View Answer

Answer 1. The shortest lead-time from raw material to finished production of an item