Exam Question
Time fence means
- 1. The shortest lead-time from raw material to finished production of an item
- 2. Ensuring accuracy of inventory records
- 3. Method used to update MRP at regular intervals
- 4. Calculating net requirements of components
View Answer
Answer 1. The shortest lead-time from raw material to finished production of an item
Practice set and Exam Quiz
Yes! You can do Online MCQ practice of Project Planning Appraisal and Control question set and give online exam quiz test for Project Planning Appraisal and Control, so you can check your knowledge. You can get MCQ Study and Exam link from home page.