Exam Question
Runout Time (ROT) used in batch processing is:
- 1. the time taken to complete the batch
- 2. the current inventory of an item divided by the demand per period for that item
- 3. the demand for the item divided by the opening inventory level
- 4. time for setup plus processing time
View Answer
Answer 2. the current inventory of an item divided by the demand per period for that item
Practice set and Exam Quiz