Exam Question

In an assembly line the total processing time per, unit is 380 seconds, and the cycle time for the line is 90 seconds. What is the minimum number of workstations required in the assembly line?

  • 1. 4 stations
  • 2. 4.22 stations
  • 3. 5 stations
  • 4. 4.2 stations

View Answer

Answer 1. 4 stations