Job A and B are waiting to be released. Both will go to work center 1. Then A will continue on to work center 3 while B will go to work center 4. Suppose that A has high priority on the first work center and center 4 is backlogged and center 4 is idle. Which order should be released first?

  • 1. Job A
  • 2. Job B
  • 3. Both Job A and Job B together
  • 4. Toss a coin and if its heads, go for Job A otherwise Job B

View Answer

Answer 1. Job A