Exam Question
Critical Ratio used in Capacity Planning and Control is:
- 1. Time to due date divided by required time for remaining operations
- 2. Time for first job divided by time for second job
- 3. Capacity consumed by the job divided by total capacity of the plant
- 4. Capacity of output divided by capacity of input
View Answer
Answer 1. Time to due date divided by required time for remaining operations
Practice set and Exam Quiz
Yes! You can do Online MCQ practice of Project Planning Appraisal and Control question set and give online exam quiz test for Project Planning Appraisal and Control, so you can check your knowledge. You can get MCQ Study and Exam link from home page.