Exam Question
If a machining center has a machine utilisation of 95% and operator efficiency of 80%, what is
the effective work centre capacity in July assuming 26 working days and 3 shifts running each day:
- 1. 472.24 hours
- 2. 472 hours
- 3. 158.08 hours
- 4. 59.28 hours
View Answer
Answer 1. 472.24 hours