Infinite loading is:
- 1. assigning jobs to work centers without considering the work center’s capacity
- 2. using Gantt chart for loading
- 3. using visual load profile for showing load
- 4. considering loading of planned orders only
View Answer
Answer 1. assigning jobs to work centers without considering the work center’s capacity