A classification system has been devised to determine how well an MRP system has been
- 1. Class C company is:
- 1. one which has MRP II in full use and the closed loop is working
- 2. one in which MRP system is working only in the computing department
- 3. one which may have MRP, capacity planning and shop floor controls working
- 4. one which uses MRP for inventory ordering but not for scheduling
View Answer
Answer 3. one which may have MRP, capacity planning and shop floor controls working