A firm uses simple exponential smoothing to forecast demand with a = 0.2. The forecast for the month of March was 500 units whereas the actual demand turned out to be 460 units. What is the forecast for the month of April?

  • 1. 489.6
  • 2. 492
  • 3. 480
  • 4. 490

View Answer

Answer 2. 492