All of the following are time phasing requirement of an MRP logic except

  • 1. Gross requirement will occur at the middle of a period
  • 2. On hand inventory will be measured at the end of a period
  • 3. Planned order release will occur at the beginning of a period
  • 4. Lead time considerations are not taken for time phasing

View Answer

Answer 4. Lead time considerations are not taken for time phasing