‘Capital Structure’ of a company refers to:

  • 1. Building structure of the unit
  • 2. Lay-out plan of installation of plant and machinery
  • 3. Ratio of ownership capital to credit capital
  • 4. None of above

View Answer

Answer 3. Ratio of ownership capital to credit capital

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

‘Control’:

  • 1. Is the first step in project management
  • 2. It follows ‘Planning’
  • 3. It follows implementation
  • 4. None of above

View Answer

Answer 3. It follows implementation

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

‘Finance for working capital is generally obtained from’:

  • 1. The State
  • 2. Industrial and Development Banks
  • 3. LIC/GIC
  • 4. Co-operative and commercial banks

View Answer

Answer 4. Co-operative and commercial banks

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

‘Industrial Finance is required’:

  • 1. For Fixed Deposits elsewhere to earn interest
  • 2. To open charitable dispensary
  • 3. For fixed assets, raw-material and to meet day to day expenses
  • 4. None of above

View Answer

Answer 3. For fixed assets, raw-material and to meet day to day expenses

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

‘Long Term’ industrial finance is procured generally:

  • 1. Directly from small savings public
  • 2. Private money lenders
  • 3. Small Finance companies
  • 4. State and Industrial development

View Answer

Answer 4. State and Industrial development

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

‘Project Finance’ is generated by way of:

  • 1. 100% Equity
  • 2. 100% Debt
  • 3. 50% Equity or 50% Debt
  • 4. As per feasibility report in this regrd

View Answer

Answer 4. As per feasibility report in this regrd

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

‘Review’ is part of

  • 1. Planning process
  • 2. Implementation process
  • 3. Budgeting process
  • 4. Controlling process

View Answer

Answer 4. Controlling process

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Question: “Devising and maintaining a workable scheme to accomplish the business need” is

  • A. Initiating process
  • B. Planning process
  • C. Executing process
  • D. Controlling proces

View Answer

Answer B. Planning process

Give online quiz test

Yes! You can also try Project Management FREE MCQ Quiz and improve your speed and knowledge

Discuss if any doubt

Exam Question

A budgeting method that begins with those who will be doing the tasks is called

  • 1. Top-down budgeting
  • 2. Bottom-up budgeting
  • 3. Program budgeting
  • 4. Zero budgeting

View Answer

Answer 2. Bottom-up budgeting

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

A buyer extends a formal invitation that contains a scope of work that seeks a response that will describe the methodology and results that will be provided to the buyer. This is called:

  • 1. Invitation to bid
  • 2. Request for information
  • 3. Request for proposal
  • 4. Request for bid

View Answer

Answer 3. Request for proposal

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

A critical path network diagram does not:

  • 1. Calculate earned-value
  • 2. Help determine the amount of float
  • 3. Calculate the duration of the whole project
  • 4. Identify the particularly important activities

View Answer

Answer 1. Calculate earned-value

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Question: A design is said to be a good design if the components are

  • A. Strongly coupled
  • B. Weakly cohesive
  • C. Strongly coupled and Weakly cohesive
  • D. Strongly coupled and strongly cohesive
  • E. Strongly cohesive and weakly coupled

View Answer

Answer E. Strongly cohesive and weakly coupled

Give online quiz test

Yes! You can also try Project Management FREE MCQ Quiz and improve your speed and knowledge

Discuss if any doubt

Exam Question

A dummy activity is required when

  • 1. The network contains two or more activities that have identical starting and ending events
  • 2. Two or more activities have different ending events
  • 3. Two or more activities have the same ending events
  • 4. Two or more activities have the same starting events

View Answer

Answer 1. The network contains two or more activities that have identical starting and ending events

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Question: A general statement of objectives is the major cause of failed efforts

  • A. True
  • B. False

View Answer

Answer A. True

Give online quiz test

Yes! You can also try Project Management FREE MCQ Quiz and improve your speed and knowledge

Discuss if any doubt

Exam Question

A Greenfield project means

  • 1. A project that is started from scratch
  • 2. An environment friendly project
  • 3. A project that produces green products
  • 4. A project that is completed at a cost less than the budgeted cost

View Answer

Answer 1. A project that is started from scratch

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

A group of related projects that are managed in a coordinated way that usually include an element of ongoing activity is called a:

  • 1. Major project
  • 2. Project office
  • 3. Program
  • 4. Group of projects

View Answer

Answer 1. Major project

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Question: A is developed using historical cost information that relates some metric to the project cost

  • A. Algorithmic cost modelling
  • B. Expert judgement
  • C. Estimation by analogy
  • D. Parkinson’s Law

View Answer

Answer A. Algorithmic cost modelling

Give online quiz test

Yes! You can also try Project Management FREE MCQ Quiz and improve your speed and knowledge

Discuss if any doubt

Exam Question

A linear responsibility chart has all the following except

  • 1. Shows who is responsible for what
  • 2. Shows critical interfaces between units that needs special coordination
  • 3. It shows who must approve what and who must report to whom
  • 4. Provides the cost and schedule of each of the task

View Answer

Answer 4. Provides the cost and schedule of each of the task

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Exam Question

A manager that manages a group of related projects is called a:

  • 1. Project manager
  • 2. Project expediter
  • 3. Program coordinator
  • 4. Program manager

View Answer

Answer 1. Project manager

Practice set and Exam Quiz

Yes! You can do Online MCQ practice of Project Management question set and give online exam quiz test for Project Management, so you can check your knowledge. You can get MCQ Study and Exam link from home page.

Discuss if any doubt

Question: A project has never happened before, and it will never happen again under the___

  • A. same conditions
  • B. Extreme case
  • C. Other condition
  • D. None of the above

View Answer

Answer A. same conditions

Give online quiz test

Yes! You can also try Project Management FREE MCQ Quiz and improve your speed and knowledge

Discuss if any doubt
1 2 3 4 5 12 13 14 15

Important note for exam preparation: Must try Online MCQ Quiz Test after practice these MCQ, so you can check your knowledge and improve efficiency. You can get link from above mention for these subjects.